News
L11 is halted by Defence, complicating the southern connection
The extension of Metro line 11 towards south-west Madrid has encountered an unexpected obstacle. An unfavourable report from the Ministry of Defence complicates the planned advance towards Cuatro Vientos and forces the Community of Madrid to study alternatives to maintain the promised connection.

The blockage affects one of the major mobility commitments of coming years. The L11 is intended to become a major Metro diagonal, capable of linking the south and east of the city with new interchange stations, growing neighbourhoods and areas that today depend heavily on cars or journeys with several transfers.
The problem is concentrated on the section towards Cuatro Vientos. Defence considers that the proposed route affects land of military interest, which prevents proceeding with the solution planned by the Community of Madrid in that area.
The regional government maintains that it is not giving up the project. The Minister for Housing, Transport and Infrastructure, Jorge Rodrigo, has assured that Metro de Madrid and the Community will intensify studies to find an alternative route that allows the final objective to be maintained.
The L11 extension is not a minor work. The complete plan seeks to create an axis of around 33 kilometres and 20 stations between Cuatro Vientos and Valdebebas, a connection intended to change how people move between neighbourhoods that now lack a direct Metro connection.
While the conflict is resolved, residents in the south remain awaiting a long-anticipated infrastructure. In areas such as Carabanchel, La Fortuna, Cuatro Vientos or neighbourhoods close to the projected axis, any delay translates into more journey time and fewer real alternatives to private transport.
The clash between administrations adds uncertainty to a project already transforming other parts of the city. L11 works are advancing through sections such as Comillas, Madrid Río and the area around Conde de Casal, where the future line promises new links with the centre and other modes of transport.
The great unknown now is whether Madrid can maintain the L11 timetable and ambition without the planned route towards Cuatro Vientos. The answer will mark the future of a line intended to ease daily journeys, connect historically less well-connected neighbourhoods and give metropolitan meaning to a network that continues to grow.